Construction Updates
Photographs:
Click here to expand and collapes As of 12th January 2011
Completion Date:
Plot 12P 008:   01/12/2010
Plot 12R 001:   15/11/2010
Plot 11P 003:   01/11/2010
Plot 11P 001:   01/11/2010
Plot 11V 001:   01/11/2010
Plot 11R 001:   15/01/2011
Plot 11V 003:   15/01/2011
Plot 11H 001:   28/02/2011
 
Dubai Land Department
       Dubai Land Department approved Land common area Site plan for JVC11PFRP001
       Dubai Land Department approved Land common area Site plan for JVC11RFRP001
       Dubai Land Department approved Land common area Site plan for JVC11VFRP001
       Dubai Land Department approved Land common area Site plan for JVC11VFRP003
       Dubai Land Department approved Land common area Site plan for JVC12PFRP008
Building Completion Certificates (BCC):
Click here to expand and collapes Scanned BCC's
Infrastructure Update:
Nakheel’s and their infrastructure contractor, Dodsal, are deploying more manpower and machinery to expedite completion of works at Jumeirah Village.
Status of Works: as of 08/05/2011
No Infrastructure works Construction Phase 1 Construction Phase 2
11P 001 11P 003 11V 001 12R 001 12P 008 11V 003 11H 001 11R 001
Developer Fortisplus’s Scope of Works:
1 Pending works All works completed All works completed All works completed All works completed All works completed All works completed Final testing & commissioning.
All works completed
2 Construction status (% completed) 100% 100% 100% 100% 100% 100% 99% 100%
3 Completion Date (as per Building Completion Certificate) Achieved on 12th July 2010 Achieved on 8th July 2010 Achieved on 3rd August 2010 Achieved on 1st July 2010 Achieved on 1st July 2010 Achieved on 22nd November 2010 Achieved on 15th December 2010 Achieved on 21st November 2010
4 Permanent water & electrical connection Water & electricity connected. Water & electricity connected. Water & electricity connected. Water & electricity connected. Water & electricity connected. Water & electricity connected. Electricity connected. Water to be connected by 30th May 2011 Water & electricity connected.
5 Handover Date 1st Nov 2010 1st Nov 2010 1st Nov 2010 15th Nov 2010 2nd Dec 2010 15th Feb 2011 15th June 2011 15th Feb 2011
Master Developer’s (Nakheel’s) Scope of Infrastructure Works:
6 Tarmac road in front of plot 1st May 2011
7 Back alleyway road on garage side 30th May 2011 15th June 2011 25th May 2011 15th June 2011
8 Interlock on front side bet. gate & main road June 2011 June 2011 June 2011 June 2011 June 2011 June 2011 June 2011 June 2011
9 Interlock on garage side bet. road & garage
10 Street lighting 25th April 2011 10th May 2011 30th May 2011 10th May 2011
11 Dewa’s laying of LV cable to plot









12 Dewa’s energising of 132KV substation to connect power to plot















13 Laying of main water pipeline for permanent water to plot 30th May 2011
14 Laying of DU telecom lines to plot
15 Water Test of main water line 10th June 2011
16 Completion of full infrastructure works in JVC Dec 2011 Dec 2011 Dec 2011 Dec 2011 Dec 2011 Dec 2011 Dec 2011 Dec 2011
Legend:
X  = To be started shortly

U  = Under process & to be completed shortly
√  = Completed